What the calculator does
- The reference price under article 44 of decree no. 2-22-431, after excessive and abnormally low offers are set aside (article 43).
- Study contracts under article 144: thresholds, technical and financial scores, ranking.
- Exact arithmetic, with no hidden rounding.
- The thresholds, the gaps and the ranking of the offers, step by step.
- The calculation stays in your browser: what you enter is neither sent nor stored.
- No registration.
How the reference price works, in short
For works, supplies and services other than studies, the evaluation committee does not simply pick the cheapest offer. It sets aside offers that are not compliant, corrects arithmetic errors, then sets aside excessive and abnormally low offers against the contracting authority's estimate (decree no. 2-22-431, articles 43 and 44).
The reference price is the arithmetic mean of the contracting authority's estimate (E) and the mean of the offers kept (M): P = (E + M) / 2 (art. 44-A). The most advantageous offer is the one closest to P from below; if no offer is below P, the one closest from above.
An offer is excessive when it is more than 20% above the estimate, and abnormally low when it is more than 20% below (works) or more than 25% below (supplies and services other than studies) (art. 44-B). An offer exactly at the threshold is kept. For study contracts there is no reference price: article 144 sets thresholds, technical and financial scores and a ranking.
Limits of the tool
- It is an educational tool: only the tender file, the consultation rules and the evaluation committee are authoritative. It is not legal advice.
- It does not predict the result of a tender: the mean of the offers, and so the reference price, can only be computed after the bids are opened.
- It does not apply the national preference of article 147.